PART - III
CONDITIONS OF CONTRACT
DEFINITIONS
1. The ‘Contract’ means the documents forming the tender and acceptance thereof and the formal agreement, if any, executed between the Cochin Shipyard Limited and the contractor, together with the documents referred to therein including these conditions, any special conditions, the specifications, designs, drawings and instructions, issued from time to time by the Engineer in charge and all these documents taken together, shall be deemed to form one contract and shall be complementary to one another.
2. In
the contractor the following expressions shall, unless the context otherwise
requires, the meanings, hereby respectively assigned to them
a)
The expression ‘works’ or ‘work’ shall, unless there be something either in the
subject or context repugnant to such construction, be construed and taken to
mean the work by or virtue of the contract, contracted to be executed whether
temporary or permanent and whether original, altered, substituted or
additional.
b)
The ‘site’ shall mean the lands / sea and / or other places on, under in or
through which work is to be executed under the contract or any adjacent land
path or street through which work is to be executed under the contract or any
adjacent land, path or street which may be allotted or used for the purpose of
carrying out the contract.
c)
The ‘contractor’ shall mean the individual or firm or Company, whether
incorporated or not, undertaking the works and shall include the legal personal
representative of such individual or the person composing such firm or company
or the successors of such firm or company and the permitted assignee of such
individual firms or company.
d)‘Government’
or ‘Government Of India’ shall mean the President of India.
e)
The ‘Engineer in Charge’ or ‘Engineer’ means the Dy. General Manager (Civil
Engineering) Cochin Shipyard Limited or any Officer appointed by him in writing
who shall supervise and be in charge of work.
f)
Company of purchase of department of Employer shall mean the Cochin Shipyard
Limited.
When the
contract so requires words importing the singular number includes the plural
number and vice versa.
g)
‘Urgent works’ shall mean any urgent measures which, in the opinion of the
Engineer-in-Charge, becomes necessary during the progress of the works to
obviate any risk of accident or failure or which become necessary for security.
CLAUSE 1: The contractor shall,
unless he is / they are exempted from payment of security deposit in individual
cases or has / have deposited the amount of security in cash or in the form of
acceptable Government Security of fixed Deposit Receipts or Guarantee Bonds of
any Scheduled Bank or State Bank Of India, permit Cochin Shipyard Limited at
the time of making of any payment to him / them for work done under the
contract to deduct 10% from the amount of each bill till the amount so deducted
along with the sum already deposited as
earnest money will amount to 10% of the total bill amount in case of a Fixed
Deposit. Receipt of any Bank if furnished by the contractor to the Cochin
Shipyard Limited as part of the security deposit and the bank goes into
liquidation or for any reason is unable to make payment against the said fixed
deposit receipt, the loss caused thereby shall fall on the contractor and the
contractor shall for with on demand furnish additional security to the Cochin
Shipyard Limited to make good the deficit.
Such deductions from Bills are to be held by Cochin
Shipyard Limited by way of security deposit.
All compensations or other sums money payable by the contractor under
the terms of this contract or any other contract or any other Account
whatsoever may be deducted from, or paid by the sale of a sufficient part of
his security deposit, or from the interest arising there from or from any sums
which may be due to or may become due to the contractor by Cochin Shipyard
Limited or any such deduction of sale as aforesaid, the contractor shall within
10 days make good the deficit in cash or guarantee Bonds (approved).
Government papers tendered as security will be
taken at 5 % (five percent) below its market price or at its face value
whichever is less. The market price of government papers would be ascertained
at the time of collection of interest and the amount of interest of the extent
of deficiency in value of the Government paper will be withheld if necessary.
CLAUSE 1 A. The work to be carried out under the
Contract shall except as otherwise provided in these conditions, include all
labour, materials, tools plant, equipment and transport which may be required
in preparation of and for and in the full and entire execution and completion
of the works. The description given in the Schedule of Works/ items, Quantities
and the Bills of Quantities, shall unless otherwise stated, be held to include
waste on materials, carriage and cartage in return of empties hoisting,
setting, fitting and fixing in position and all other labour necessary in and
for the full and entire execution and completion as aforesaid in accordance
with good practice and recognized principles.
CLAUSE 2. The time allowed for carrying out the work as
entered in the tender shall be strictly observed by the contractor and shall be
deemed of the essence of the contract on the part of the contractor and shall be
reckoned from the fifteenth day after the date on which the order to commence
the work is issued to the contractor or from the date of handing over the site
whichever is later.
As soon as possible after the
Contract is concluded, the Engineer-in-charge and the contractor shall agree
upon a Time and Progress Chart. The Chart shall be prepared in relation to the
time stated in the contract documents for completion of the items or groups of
items of work and / or the contract as a whole. It shall indicate the forecast
of the dates of commencement and completion of various traders or sections of
the work and may be amended as necessary by agreement between the
Engineer-in-charge and the contractor within the limitation of time imposed in
the contract documents.
The work shall throughout the
stipulated period of the contract be proceeded with all due diligence. If the
contractor fails to complete the works and clear the site on or before the
contract on extended date (s) / period (s) completion, he shall, without
prejudice to any other right or remedy of Cochin Shipyard Limited on account of
such breach pay as agreed compensation, amount calculated as stipulated below
(or such smaller amount as may be fixed by the Engineer-in-charge) on the
contract value of the whole work or on the contract value of the item or group
of items of work for which a separate period of completion is given in the
contract and of which completion is delayed, for every week that the whole of
the work on the item or group of items of work concerned remains uncompleted,
even though the Contract as a whole be completed by the contract or extended
date of completion. For this purpose the term Contract value shall be the value
at Contract rates of the work as ordered including the estimated value of all
deviations ordered.
|
a) |
Completion period (as originally stipulated or as extended) |
- |
@ 1 percent per week not exceeding 6 months. |
|
b) |
Completion period (as originally stipulated or as extended) |
- |
@ ½ percent per week exceeding 6 months and not exceeding 2 years. |
|
c) |
Completion period (as originally stipulated or as extended) |
- |
@ ¼ percent per week exceeding 2 years. |
When the delay is not a full week
or in multiples of a week by involves a fraction of week, the compensation
payable for that fraction shall be proportional to the number of days involved.
Provided always that the total amount of compensation for delay to be paid under this Condition shall not exceed the under noted percentage of the contract value or of the contract value of the item or group of items of work for which separate period of completion is given:
|
a) |
Completion period (as originally stipulated or as extended) not exceeding 6 months. |
- |
10 percent |
|
b) |
Completion period (as originally stipulated or as extended exceeding 6 months and not exceeding 2 years) |
- |
7½ percent |
|
c) |
Completion period (as originally stipulated or as extended) exceeding 2 years |
- |
5 percent |
The amount of
compensation may be adjusted or set off against any sum payable to the
contractor under this or any other contract with Cochin Shipyard Limited.
2a. (i) From the
commencement to the completion of the works, the contractor shall take full
responsibility for the care thereof and all temporary works and in case any
damage, loss or injury shall happen to the works or to any part thereof or to
temporary works from any cause whatsoever (save and except the expected risks
as defined in sub clause (ii) of this clause) shall at his own cost, repair and
make good the same so that at completion the works shall be in good order and
condition and in conformity in every respect with the requirements of the
contract and the instruction of the Engineer-in-charge. In the event of any such damage loss or
injury happening from any of the excepted risks, the contractor shall if and to
the extent required by the Engineer-in-charge repair and make good the same as
aforesaid at the cost of the Cochin Shipyard Limited. The contractor shall also be liable for any damage to the works
occasioned by him in the course of any operations carried out by him for the
purpose of complying with his obligation under Clause 22 and 25.
(ii) “Excepted
risks” are war hostilities (whether war be declared or not) invasions, act of
foreign enemies, rebellion, revolution, insurrection or military, usurped civil
war or otherwise then among the contractor’s own employees), riot commotion or
disorders.
2b. Without
limiting his obligations and responsibilities under Clause 2 (a) (i) above, the
contractor shall insure in the joint names of the Cochin Shipyard Limited and
the contractor against any loss or damage from whatever cause arising (other
than the excepted risks) for which he is responsible under the terms of the
contract and in such manner that the employer and the contractor are covered
during the period of construction of the works and for any loss or damage
occasioned by the contractor in the course of any operations carried out by him
for the purpose of complying with his obligations under Clause 22 and 25, (a)
the works and temporary works to the full value of such works executed from time
to time (b) materials, construction plant and other things brought on to
constructional plants and things.
The contractor
shall indemnify and keep indemnified Cochin Shipyard Limited against all losses
and claims for injuries or damage to any person or any property whatsoever
which may arise out of or in consequence of the construction and maintenance of
the works and against all claims, demands, proceedings, damages, costs, charges
and expenses whatsoever in respect of or in relation thereto. Provided always that nothing herein
contained shall be deemed to render the contractor liable for or in respect of
or to indemnify Cochin Shipyard Limited against any compensation or damage
caused by the excepted risks.
Before
commencing execution of the work the contractor shall, without in any way
limiting his obligations and responsibilities under this condition insure
against any damage, loss or injury which may occur to any property (excluding
that of Cochin Shipyard Ltd., but including the Cochin Shipyard Limited
building rented by the Contractor wholly or in part and any part of which is
used by him for storing combustible materials), or to any person (including any
employee of Cochin Shipyard Limited) by or arising out of carrying out of the
contract.
The contractor
shall at all times indemnify Cochin Shipyard Limited against all claims, damage
of compensation under the provision of payment of wages ACT 1936, minimum Wages
Act 1943, Employer’s Liability Act 1988, the Workmen’s Compensation Act 1923;
Industrial Disputes Act 1947, and Maternity Benefit Act 1961, or any
modification thereof or any other law relating thereto and rules made there
under from time to time or as consequence of any accident or injury to any
workman or other person in or about the works, whether in the employment of the
Contractor or not, save and except where, such as accident or injury has result
from any act of Cochin Shipyard Limited, their agents or servants, and also
against all costs, charges and expenses of any suit, action or proceeding,
arising out such accident or injury and against all sum or sums which may with
the consent of the contractor be paid to compromise or compounds any such
claims without limiting his obligations and liabilities as above provided, the
contractor shall insure against all claims, damages of compensation payable
under the Workmen’s Compensation Act, 1923 or any modification thereof or any
other law relating thereto.
The aforesaid
insurance policy/ policies shall provide that they shall not be cancelled till
the Engineer-in-charge has a greed to their cancellation.
The contractor
shall prove to the Engineer-in-charge from time to time that he has taken out
all the insurance policies referred to above and has paid the necessary premia
for keeping the policies alive till expiry of the Defects Liability Period
specified in Clause 25.
The contractor
shall ensure that similar insurance policies are taken out by his subcontractor
(if any) and shall be responsible any claims or losses Cochin Shipyard Limited,
resulting from their failure to obtain adequate insurance protection
thereof. The contractor shall produce
or cause to be produced by his sub-contractor (if any) as the case may be the
relevant policy or policies and premium receipt and when required by the
Engineer-in-charge.
If the
Contractor and/ or his sub-contractor (if any) shall fail to effect and keep in
force the insurance referred to above or any other insurance which he/ they may
be required to effect under the terms of Contract and in any such case Cochin
Shipyard Limited may, without being bound to, effect and keep in force any such
insurance and pay such premia as may be necessary for that purpose and from
time to time deduct the amount so paid by Cochin Shipyard Limited from any
moneys due or which may become due to the Contractor or recover the same as a
debt due from the contractor.
All insurances
to be effected by the contractor and / or his sub-contractor (if any) shall be
taken out only with the insurance company or companies approved by Cochin
Shipyard Limited and this approval to any particular insurance company shall
not be unreasonably with held.
2c. If the
contractor shall fail to effect and keep in force the insurance referred to
above or any other insurance which he may be required to effect under the terms
of contract, than and in any such case the Engineer-in-charge may effect and
keep in force, any such insurance and pay such premia as may be necessary for
that purpose and from time to time deduct the amount so paid by the
Engineer-in-charge as aforesaid from any money due or which may become due to
the contractor or recover the same as a debt due to the contractor.
CLAUSE 3: The Engineer-in-charge may without prejudice to his right against the contractor in respect of any delay or inferior workmanship or otherwise or any claims for damage in respect of any breaches of the contract and without prejudice to any right or remedies under any of the provisions of this contract or otherwise and whether the date for completion has or has not elapsed by notice in writing absolutely determine the contract in any of the following cases.
i.
If the contractor having been given by the Engineer-in-charge a notice
in writing to rectify, reconstruct or replace any defective work or that the
work is being performed in any inefficient or otherwise improper or unworkman
like manner shall omit to comply with the requirements of such notice for a
period of seven days thereafter or if the contractor shall delay or suspend the
execution of the work so that either in the judgement of the Engineer-in-charge
(which shall be final and binding) he will be unable to secure completion of
the work by the date for completion or he has already failed to complete to the
work by that date.
ii.
If the contractor being a company shall pass a resolution or the court
shall make an order that the company shall be wound up or if a receiver or a
manager on behalf of a creditor shall be appointed or if circumstances shall
arise which entitle the court of creditor to appoint a receiver or a manager or
which entitle the court to make a winding up order.
iii.
If the contractor commits breach of any terms and conditions of this
contract.
iv.
If the contractor commits any acts mentioned in Clause 36 hereof.
When the contractor has
made himself liable for action under any of the case aforesaid the
Engineer-in-charge on behalf of the Cochin Shipyard Limited have powers.
a)
To determine or rescind the contract as aforesaid (of which termination
or rescission notice in writing to the contractor under the hand of the
Engineer-in-charge shall be conclusive evidence). Upon such determination or
rescission the security deposit of the contractor shall be liable to be
forfeited and shall be absolutely at the disposal of Cochin Shipyard Limited.
b)
To employ labour and to supply materials to carry out the works or any
part-of the work debiting the contractor with the cost of the labour and the
price of the materials (of the amount of which cost and price certified by the
Engineer-in-charge shall be final and conclusive against the contractor and
crediting him with the value of the work done in all respects in the same
manner and at the same rates as if it had been carried out by the contractor,
under the terms of his contract. The
certificate of the Engineer-in-charge as to the value of the work done shall be
final and conclusive against the contractor, provided always that action under
the sub clause shall only be taken after giving notice in writing to the
contractor. Provided also that if the
expenses incurred are less than the amount payable to the contractor at his
agreement rates, the difference should not be paid to the contractor.
c)
After giving notice to the contractor to measure up the work of the
contractor and to take such part thereof as shall be unexecuted out of his
hands and to give it to another contractor to complete in which case any
expenses which may be incurred in excess of which would have been paid to the
original contractor if the whole work had been executed by him (of the amount
of which excess the certificate in writing of the Engineer-in-charge shall be
final and conclusive) shall be borne and paid to the original contractor and
may be deducted from any money due to him by Cochin Shipyard Limited under the
contract or on any other accounts whatsoever or from his security deposit or
the proceeds of sales thereof or a sufficient part thereof as the case may be.
In
the event of any one or more of the above courses being adopted by the
Engineer-in-charge the contractor shall have no claim to compensation for any
loss sustained by him by reason of his having purchase or procured any material
or entered into any engagement or made any advance on account or with a view to
the execution of the work or the performance of contract. And in case action is taken under any of the
provision aforesaid, the contractor shall not be entitled to recover/ or be
paid any sum for any work thereto actually performed under this contract unless
and until the Engineer-in-charge has certified in writing the performance of
such work and the value payable in respect thereof and he shall only be
entitled to be paid the value so certified.
CALUSE 3 A: The Contractor shall take necessary steps to
ensure That all persons employed on any
work in connection with this contract have noticed that the Indian Official Secret
Act 1923 (XIX 1923) applies to them and shall continue so to apply even after
the execution of such works under other contract.
CLAUSE
4 (i) All operations necessary for the execution of the works and for the
construction of any temporary works shall so far as compliance with the
requirements of the contract permits, be carried on so as to not to interfere
unnecessarily or improperly with the contractors of the company, the public
convenience or the access to use and occupation of public or private roads and
footpaths or to the properties whether in the possession of Government or of
other parties and the contractor shall serve harmless and indemnified the
Cochin Shipyard Limited in respect of claims, demands, proceedings, damage,
costs, charges and expenses whatsoever arising out of or in relation to any
such matters in so far as the contractor is responsible thereof.
(ii)
The works and temporary works shall be carried out in such a manner as not
interfere with the ships or other vessels plying in the area or endanger or
interfere with the traffic whether by road, rail or water and other normal
operations.
(iii)The contractor shall in accordance with the requirements of the Engineer-in-charge afford all responsible opportunities for carrying out their works to any other contractor employed by the Shipyard or on near the site of any work not included in this contract or of contract which the Shipyard may enter into connection with or ancillary to the work. The Contractor shall construct and maintain at his own cost any approach road and access roads to the site as may be necessary and shall allow free use of the same to the Shipyard or any of the Shipyard’s other contractors who may be working in the vicinity.
CLAUSE
4 A: The contractor shall comply with and give all notice required under any Government authority,
instrument rule or order made under any Act of Parliament, State Laws or any
Regulation or Bye- laws of any Laws
authority relating to the works. He
shall before making any variation
from the contract drawings necessitated by such compliance, give to the
Engineer-in-charge a written notice giving reasons for the proposed variation
and obtain in the Engineer-in-charge’s instructions thereon.
The contractor shall pay and
indemnify Cochin Shipyard Limited against any liability in respect of any fees
or charges payable under any Act of Parliament, State Laws or any Government
Instruments Rule or Order any Regulation or Bye-laws local authority in respect
of the works.
CLAUSE 4 B: Subject as otherwise
provided in this Contract all notices to be given on behalf of Cochin Shipyard
Limited and all other actions to be taken on its behalf may be given or taken
by the Engineer-in-charge or any
officer for the time being entrusted with the functions duties and powers of
the Engineer-in-charge.
All instruction, notices and communications etc. under the Contract shall
Be given in writing and if sent
by registered post to the last known place of abode or business of the
Contractor shall be deemed to have served on the date when in the ordinary
course of post these would have been delivered to him.
The Contractor or his agent
shall be in attendance at the site(s) during all working hours and shall
superintend the execution of the works with such additional assistance in each
trade as Engineer-in-charge may be consider necessary. Orders given to the Contractor’s Agent shall
be considered to have the same force as if they had been given to the
contractor himself.
The Engineer-in-charge shall
communicate or confirm his instructions to the contractor in respect of the
execution of work in a ‘work Site Order Book’ maintained in the officer of the
Engineer-in-charge and the Contractor or his authorized representative shall confirm
receipt of such instruction by signing the relevant entries in this book. If required by the contractor he shall be
furnished a certified true copy of such instructions(s).
CLAUSE 5. In any case in which any of the powers
conferred upon the Engineer-in-charge
by Clause 3 hereof, shall have become exercisable and the same shall not the exercised, the non-exercise thereof
shall not constitute a waiver of
any of the conditions hereof and such powers shall not withstanding be exercisable in the event of any future case
of default by
the contractor and the liability of the contractor for compensation shall
remain unaffected. In the event of the
Engineer-in-charge putting in force all or any of the powers vested in him
under Clause 3 he may, if so desires,
after giving a notice in
writing to the
contractor, take possession of
(or at the sole discretion of the Engineering-in-charge which shall be final)
use as on hire (the amount of the hire money being or also in the final determination of the Engineer-in-charge) shall
or any tools, plant, materials and stores, in or upon the works, or the
site thereof, belonging to the
contractor, or procured by the contractor and intended to be used for the execution
of the work or any part thereof, paying or allowing for the same in account at
the contract rates, or in the case of these not being applicable, at current
market rates to be certified by the Engineer-in-charge, whose certificate
thereof shall be final, otherwise the contractor or his clerk of the works,
foreman or other authorized agent to remove such tools plant materials or
stores from the premises (within a time to be specified in such notice), and in
the event of the contractor failing to comply with any such requisition, the
Engineer-in-charge may remove them at the contractor’s expense or sell them by
auction or private sale on account of the contractor and at his risk in all
respects and the certificates of the Engineer-in-charge as to the expense of
any such removal and the amount of the proceeds and expense of any such sale
shall be final and conclusive against the contractor.
CLAUSE 6 : If the Contractor shall desire an
extension of time for completion of
the work on the ground of his having been unavoidably in its execution or on
any other ground, he shall apply in writing to the DGM (Civil Engineering)
within 3 days of the date of hindrance on account of which he desire such
extension as a foresaid, and the DGM (Civil Engineering) shall, if in his
opinion (which shall be final) reasonable grounds he shown therefore authorize
such extension of time, if any, as may in his opinion necessary or proper.
CLAUSE 6 A: The contractor shall arrange at his own
expenses tools of plant and equipment (referred to as T.& P) required for
execution of the work.
CLAUSE 7: Within ten days of the completion of the work,
the contractor shall give notice of such completion to the Engineer-in-charge
and within thirty days the receipt of such notice the Engineer-in-charge shall
inspect the work and if there is no defect in the work shall furnish the
contractor with a certificate of completion, otherwise a provisional
certificate of completion indicating defects (a) to be rectified by the
contractor / and or (b) for which payment will be made at reduced rates shall
be issued but no certificate of completion provisional or otherwise, shall be
issued nor shall the work be considered to be complete until the contractor
shall have removed from the premises on which the work shall be executed all
scaffolding surplus materials, rubbish and all huts and sanitary arrangements
required for his/their work /people on the site in connection with the
execution of the works and shall have been erected or constructed by the
contractor (s) and cleaned off the debris from all wood works, doors, windows,
walls, floors or other parts of any building, in, upon or about which the
execution thereof and not until the work shall have been measured by the
Engineer-in-charge may at the expense of the contractor remove such scaffolding,
surplus materials and rubbish etc. and dispose of the same as he thinks fit and
clean off such dirt as aforesaid and the contractor shall have no claim in
respect of any such scaffolding or surplus materials as aforesaid except for
any sums actually realized by the sale thereof.
CLAUSE 8: No payments shall be made for works estimated to
cost less than rupees five
thousand, till after the whole of the works shall have been completed and
certificate of completion given. But
in the case of works estimated to cost more than
rupees five thousand, the contractor shall on submitting the bill thereof be
entitled to receive a monthly payment
proportionate to the part
thereof been shall
be final and conclusive against the contractor But
all such intermediate payments shall be regarded as payments by way of advance
against the final payment only and not as payments for work actually done and
completed and shall not preclude the requiring of bad, unsound and imperfect or
unskilled work to be removed and taken away and reconstructed or re-erected or
be considered as an admission of the due performance of the contract, or any
part thereof in any respect or the occurring of any claim, nor shall it
conclude, determine or affect in any way the power of the Engineer-in-charge
under these conditions or any of them as to the final settlement and adjustment
of the accounts or otherwise, or in any other way vary or affect the contract.
The final bill shall be submitted by the contractor within one month of the
date fixed for completion of the work or of the date of the contractor within
one month of the date fixed for completion of the work or of the date of the
certificate of completion furnished by the Engineer-in-charge and payment shall
be made within three months if the amount of the Engineer-in-charge and payment
shall be made within three months if the same exceeds Rs. 2 lakhs of the
submission of such bill. No further claims shall be made by the contractor
after submission of the final and these shall deemed to have been waived and
extinguished. If there shall be any dispute about any item or items of the work
then the undisputed item or items only shall be paid within the said period of
three months as the case may be. The contractor shall submit a list of the
disputed items within thirty days from the disallowance thereof and if he fails
to do this, his claim shall be deemed to have been fully waived and absolutely
extinguished.
CLAUSE 9: A bill shall be
submitted by the contractor each month on before the date fixed by the
Engineer-in-charge for all works executed in the previous month, and the
Engineer-in-charge shall take or cause
to be taken the requisite measurement for the purpose of having the same
verified, and the claim, as far as admissible, adjusted as far as possible,
before the expiry of ten days from the presentation of the bill. If the
contractor does not submit the bill within the date fixed as aforesaid, a
subordinate to measure up the said work in the presence of the contractor whose
countersignature to the measurement list will be sufficient warrant, and the
Engineer-in-charge may prepare a bill from such list.
CLAUSE 10: Before taking any measurement of any work as has been
referred to in clause 7,8 and 9 hereof the Engineer-in-charge or a subordinate
deputed by him shall give reasonable notice to the contractor. If the
contractor fails to attend at the measurements after such notice or fails to
countersign or to record the difference within a week from the date of measurement in the manner required by the
Engineer-in-charge then in any such
event the measurements taken by the Engineer-in-charge or by the subordinate
deputed by him as
the case may
be shall be
final and binding on the
contractor and shall have no right to
dispute the same.
CLAUSE 11: The contractor shall
submit all bills, on the printed forms to be
had on application at the office of the Engineer-in-charge and the charge in
the bills shall always be entered at the rates specified in the tender or in the
case of any extra work ordered in pursuance of these conditions and not
mentioned or provided for in the tender at the rates hereinafter provided for
such work. The cost of printed forms shall be borne by the contractor.
CLAUSE 12: Payment due to the contractor may, if so
desired by him, be made of his
bank instead of direct to him provided that the contractor furnishes to the
Engineer-in-charge (1) an authorisation in the form of a legally valid document
such as power of attorney conferring authority on the bank to receive payment
and (2) his own acceptance of the correctness of the account made out as being
due to him by CSL or his signature on the bill or other claim by payment to the
Bank. While the receipt given by such bank shall constitute a full and
sufficient discharge for the payment, the Contractor should wherever possible,
present his bill receipted and discharged through his bankers.
Nothing herein contained shall operate to create in
favour of the bank any rights or equities vis-à-vis the Cochin Shipyard Limited.
CLAUSE 13: Store supplied by Cochin Shipyard Limited if
the specification or schedule of items provided for the use of any special
description of materials to be supplied from Engineer-in-charge’s stores, or if
it is required that the contractor shall use certain stores to be provided by
the Engineer-in-charge, as shown in the schedule of materials hereto annexed,
the contractor shall be bound to procure and shall be supplied such materials
and stores as are from time to time required to be used by him for the purpose
of the contract only and the value of the full quantity of materials and stores
so supplied at the rates specified in the said schedule of materials may be set
off or deducted from any then due, or there after to become due to the
contractor under the contract, or otherwise, or against the security deposit,
or the proceeds of the sale thereof if the same is held in Government
Securities the same or a sufficient portion thereof being in this case sold for
the purpose. All materials so supplied to the contractor shall remain the
absolute property of Cochin Shipyard Limited, and shall not be removed on any
account from the site of the work and shall be at all time open to inspection
by the Engineer-in-charge. Any such materials remaining unused and in perfectly
good condition at the time of the completion of determination of the contract
shall be returned to the Engineer-in-charge at a place directed by him if any a
notice in writing under his hand he shall so require, but the contractor shall
not be entitled to return any such materials unless with such consent and shall
have no claim for compensation on account of any such materials so supplied to
him as aforesaid not being used by him or for any wastage in or damage to an such
materials. Provided that the contractor shall in no case be entitled to any
such materials so supplied to him as aforesaid not being used by him or for any
wastage in or damage to any such materials. Provided that the contractor shall
in no case be entitled to any compensation or damages on account of any delay
in supply or non-supply thereof all or any such materials and stores provided
further that the contractor shall be bound to execute the entire work if the
materials are supplied by the Cochin Shipyard Limited within the scheduled time
for completion of the work plus 50% thereof (Schedule time plus 6 months if the
time of completion of the work exceeds 12 months) but if a part only of the
materials has been supplied within be possible with the materials and stores
supplied in he aforesaid period. For the completion of the rent of the work,
the contractor shall be entitled to such extension of time as may be determined
by the Engineer-in-charge whose decision in this regard shall be final.
CLAUSE 14: The Engineer-in-charge
shall have full powers to require the removal from the premises of all
materials which in his opinion are not in accordance with the specifications
and in case of default the Engineer-in-charge is to be at liberally to employ
other persons to remove the same without being answerable or accountable for
any loss or damage that may happen or arise to such materials. The
Engineer-in-charge shall also have full powers to require other proper
materials to be substituted therefore and in case of default the
Engineer-in-charge may cause the same to be supplied and all costs which may
attend such removal and substitution are to be borne by the Contractor.
CLAUSE 15: The Contractor on
signing an indenture in the form to be specified by the Engineer-in-charge
shall be entitled to be paid during the progress of the execution of the work
75% of the purchase price of any materials actually acquired for the work which
are in the opinion of the Engineer-in-charge non perishable are in accordance with
the contract, are necessary for the work, are not in excess of requirements and
which have been brought on the site in connection there with and are adequately
stored and / or protected against damage by weather or other cause but which
have not at the time of advance been incorporated in he work. In such cases the
Contractor should produce documents in support of the price paid by him and the
decision of the Engineer-in-charge as regards the reasonableness of the price
shall be final. In case when documentary evidence of price cannot be readily
produced, Engineer-in-charge may assess a reasonable price. When materials on
account of which an advance has been made under this sub-clause are
incorporated in the work the amount of such advance shall be deducted from the
next payment made under any of the clause or clause of this contract.
CLAUSE 16: If during the progress
of the works, the price of any materials incorporated in the works (not being a
material supplied from the Engineer-in-charge’s stores in accordance with
clause 13 thereof) and / or wages of labour increase as a direct result or the
coming into force of any fresh law, or statutory rule or order ( but not due to
any changes in Sales Tax) and such increase exceeds ten percent of the price
and / or wages prevailing at the time of acceptance of the tender for the work,
and the contractor thereupon necessarily and properly pays in respect of that
material (incorporated in the works) such increased price and / or in respect
of labour engaged on the execution of the work such increased wages, then the
amount of the contract shall accordingly be varied, provided always that any
increase so payable is not in the opinion of the Administrative head (whose
decision shall be final and binding) attributable to delay in the execution of
the contract, within the control of the contractor. If during the progress of
the works, the price of any materials incorporated in the works (not being a
material supplied from the Engineer-in-charge’s Store in accordance with Clause
13 here of) and / or wages of labour is decreased as result of the coming into
force of any fresh law, or statutory rule or order (but not due to any changes
in Sales Tax) and such decrease exceeds ten percent of prices and / or wages
prevailing at the time of acceptance of tender for the work Engineer shall in
respect of materials incorporated in the works (not being materials supplied
from the Engineer-in-charge’s Store in accordance with Clause 13 hereof) and /
or labour engaged on the execution of the work after the date of coming in to
force of such law, statutory rule or order be entitled to deduct from the dues
of the contractor such amount as shall be equivalent to difference between the
prices of materials and / or wages as they prevailed at the time of acceptance
of tender for the work minus ten percent thereof and the prices of materials
and / or wages of labour on the coming into force of such law, statutory rule
or order.
The contractor shall, for the
purpose of this conditions, keep such books of account and other documents as
are necessary to show the amount of any increase claimed or reduction available
and shall allow inspection of the same by a duly authorized representative of
Engineer, and further shall, at the request of the Engineer –in-charge,
furnish, verified in such a manner as the Engineer-in-charge may require, any
documents so kept and such other information as the Engineer-in-charge may
require. The Contractor shall within a reasonable time of his becoming aware of
any alteration in the price of any such materials and / on wages of a labour,
give notice thereof to the Engineer-in-charge stating that the same is given
pursuant of this condition together with all information relating thereto which
he may be in a position to supply.
CLAUSE 17: The contractor shall
treat all material obtained from dismantling of a structure, excavation of the
site for a work etc., as Cochin Shipyard Limited property and such materials
shall be duly handed over to the Engineer-in-charge or disposed of to the best
advantage of Cochin Shipyard Ltd, according to the instructions in writing
issued by the Engineer-in-charge.
CLAUSE 18: The contractor shall execute the whole and every part of
the work in the most substantial and workmanlike manner both as regards
materials and otherwise, in every respect in strict accordance with the
specifications. The contractor shall also conform exactly fully and faithfully
to the designs, drawings, and instructions in writing in respect of the work
signed by the Engineer-in-charge and the contractor shall be furnished free of
charge one copy of specification and of all such drawings and instructions as
are not included in the specification mentioned elsewhere in the contract.
CLAUSE 19: The Engineer-in-charge shall have power to make
any alteration, in omissions from, additions to or substitutions for, the
original specifications drawings, designs and instructions, that may appear to
him to be necessary during the progress of the work and the contractor shall
carry out the work in accordance with any instructions which may be given to
him in writing signed by the Engineer-in-charge, and such alterations,
omission, additional or substitutions shall not invalidate the contract any
altered, additions, or substituted work which the contractor may be directed to
do in the manner above specified as part of the work shall be carried out by
the contractor on the same conditions in all respects on which he agreed to do
the main if the Contractor finds after examining the plans, Specification and
Site conditions that extras are
involved, he should give notice to the Engineer to this effect and shall
proceed with the execution of the extra item (altered, additional or
substituted items) only after receiving instructions in writing from the
Engineer-in-charge. There shall be an order in writing to executive to the
extra item of work duly signed by the Engineer-in-charge before the
commencement. The Engineer-in-charge reserves the right to execute any extra
items of work beyond the scope of the contract by other agencies. The time for
the completion of the work shall, if requested by the contractors, be extended
the proportion that the altered, additional or substituted work bears to the
original contract work, and the certificate of the Engineer-in-charge shall be
conclusive as to such proportion. Over
and above this, further period to the extent of 25 percent of such extension
shall be allowed to the contractor if found reasonable by the Engineer-in-charge. The rate for such
additional altered or submitted work under this clause shall be worked out in
accordance with the following provision in their inspective order.
(i) If the rates for the additional, altered or substituted
work are specified in the contract for the work, the contractor is bound to
carry out the additional altered or substituted work at the same rates as are
specified in the contract for the work. In the case of compo-site tenders where
two or more schedules of quantities may form part of the contract the
applicable rate shall be taken from the schedule of quantities of that
particulars part in which the deviation is involved, failing that at the lowest
applicable rate for the same item of work in the other schedule of quantities.
(ii) If the rate for any altered
additional or substituted work are specified in the schedule of quantities the
rate for that item shall be derived from the rate for the nearest similar item
specified therein . in case of composite tenders where two or more schedule of
quantities from part of the contract, the rate shall be derived from the
nearest similar item in the Bill of Quantities of the particulars part of the
works in which the deviation is involved failing that from the lowest of
nearest similar items in other schedule of quantities.
(iii) If the altered, additional or
substituted item includes any work for which no rate is specified in the
contract and the rate for work cannot be derived from the similar class of work
in the contract than such work shall be carried out at the rate provided for in
the Kerala State P.W.D ………….………………..Schedule of Rates applicable to Ernakulam
District Tender excess or tender deduction will be applied.
(iv) If the rate for any altered,
additional or substituted item of work cannot be determined in the manner
specified in Sub-Para (i) to the (iii) above then the rate for such items of
work shall be derived from the Schedule of Rate specified in sub-para (iii)
without applying tender excess or deduction. Provided always that if rate (s)
for the such part (s) of an item (s) is / are not specified in the Schedule of
Rate the rate the rate (s) for such part (s) shall be determined by the
Engineer-in-Charge on basis of the purchase price as supported by the vouchers
unless the Engineer-in-charge finds the purchase price as supported by the
vouchers unless the Engineer-in-charge fro the purchase price unreasonable. In
the alter event the price shall be determined on the basis of market rate (s)
prevailing during the fortnight following the date of the order. Contractor’s
profit @ 10% is to be added to such items where rate has been determined based
on prevailing market rate.
(v) If the rates for the altered,
additional or substituted work cannot be determined in the manner specified in
sub-clause (i) to (iv) above than the contractor shall, within 14 Days of the
date of receipt of order to carry out the work, inform the D G M (Civil Engg.)
of the rate which in his intention to charge for such class of work, supported
by analysis of the rate or rates claimed, and the D G M (Civil Engg.) shall
determine the rate or rates on the basis of prevailing market rates, and pay
the contractor accordingly. In the event of the contractor failing to inform the
Engineer-in-charge within the stipulated period of time, the rate which he
proposes to claim, the rate for such item, shall determined by the
Engineer-in-charge on the basis of his assessment of the market rates.
Contractor’s profit at 10% is to be added to such items where the rate has to
be determined based on prevailing market rate. However, the Engineer-in-charge,
by notice in writing, will be at liberty to cancel his order to carry out such
class of work and arrange to carry out in such manner as he may consider
advisable, but under no circumstances, the contractor shall suspend the work on
the plea of non settlement of rates of items falling under the clause.
(vi) The deviations ordered on item
of any individual trade included in the contract excluding that of foundation
shall no exceed plus 25% of the value of the trade in the contract as a whole.
The contractors shall execute the work upto the above deviation at the quoted
rate for the work. The work in foundation consists of all items below ground
surface, quantities of which may vary due to site or soil conditions.
Notes: -
Individual trade means the trade
sections in to which a schedule of quantities annexed to the agreement has been
divided or, in the absence of any such division, the individual sections of the
Kerala state P W D Schedule of rate specified above, such as excavation and
earth work, concrete, wood work and joinery etc.
The rates of any such work except
the items relating to foundation, which is in excess of the deviation limit of
25%, shall be determined in accordance with the provision contained in Clause –
20.
Clause 20: In the case of contracted or substituted item which individually exceed the quantities stipulated in the contract by more than the deviation limit except the items relating to foundation work, which the contractor, ie, required to under clause 19 above, the contractor shall, with in 7 days from the receipts or order claim revision of the rates supported by proper analysis in respect of such items for quantities in excess of the deviation limit, not withstanding the fact that the rates for such items exist in the tender for the main work or can be derived in accordance with the provision of sub clause 19 and the Engineer-in-charge may revise their rates, having regard to the prevailing market rate and the contractor shall be paid in accordance with the rate so fixed. The Engineer-in-charge shall, however, be at liberty to cancel his order to carry out such increased quantities of work by giving notice in writing to the contract and arranged to carry it out in such manner as he may consider advisable. But under no circumstances the contractor shall suspend the work on the plea of non – settlement rates of items falling under this clause. All the provision of the preceding paragraph shall equally apply to the decrease in the rates for such items exist in the tender for the main work or can be derived in accordance with the provisions of sub-clause (2) of the preceding clause 19, and the Engineer-in-charge may revise such rates having regards to the prevailing market rates.
CLAUSE 20A:
(a) The contractor
shall on receipt of the order in writing of the Engineer-in-charge suspend the
progress of the work, or any part thereof for such time and in such manner as
the Engineer-in-Charge may consider necessary for any of the following reasons.
(i) On account of any default on part of the
contractor.
(ii) For proper execution of the works or part
there of for reasons other than the default the contractor or
(iii) For safety of the works or part thereof.
The contractor shall, during such suspension, properly
protect and secure the works to the extent necessary and carry out the
instructions given in that behalf by the Engineer-in-Charge.
(b) If the Suspension is ordered for
reasons (ii) and (iii) in the above para.
(i)
The Contractor shall be entitled
to an extension of the time equal to the period of every such suspension PLUS
25 % for completion of the item or group of items of work for which a separate
period of completion is specified in he contract and of which the suspended
work forms a part, and
(ii) If he total period of all
such suspension in respect of an item or group of them of work for which a separate
period of completion is specified in the contract exceeds thirty days, the
contractor shall, in addition, be entitled to compensation, as the
Engineer-in-charge may consider reasonable, in respect of salaries and / or
wages paid by the contractor to his employees and labour at site, remaining
idle during the period of suspension, adding there to a suitable percentage to
be decided by the Engineer-in-charge to cover indirect expenses of the contract.
(c) If the works or part thereof is
suspended on he orders of the Engineer-in-charge for more than three months at
a time, except when suspension is ordered for reason (i) in sub-para (a) above,
the Contractor may after receipt of such order serve a written notice on the
Engineer-in-charge requiring permission within fifteen days from receipt by the
Engineer-in-charge of the said notice, to proceed with works or part thereof in
regard to which progress has been suspended and if such permission is not
granted within that time, the Contractor, if the intends to treat the
suspension, where it affect only a part of the works as an omission of such
part by Government under Condition 19 and 20 or where it affects the whole of
the works, as an abandonment of work by Cochin Shipyard Limited, shall within
ten days of expiry of such period of 15 days give notice in writing of his
intention to the Engineer-in-charge. In the event of the Contractor treating
the suspension as an abandonment of the Cochin Shipyard Limited, he shall have
no claim to payment of any compensation on account of any profit or advantage
which he may have derived from he execution of the work in full but which he
could not derive in consequence of the abandonment. He shall, however, be
entitled to compensation, as the Engineer-in-charge may consider reasonable, in
respect of salaries and / or wages paid by him to his employees and labour at
site, remaining idle in consequence and of materials collected which could not
be utilized on the works, adding to the total thereof a suitable percentage to be
decided by the Engineer-in-charge to cover indirect expenses of the Contractor.
CLAUSE 20 B: In any urgent work
(in respect where of the decision of the Engineer-in-charge shall be final and
binding) becomes necessary and the contractor is unable or unwilling at once to
carry it out the Engineer-in-charge may by his own or other work people carry
it out as he may consider necessary, If the urgent work shall be such as the
contractor is liable under the contract to carry out at his expenses, all
expenses incurred on it by Cochin Shipyard Limited, shall be recoverable from
the contractor and he adjusted or set off against any sum payable to him.
CLAUSE 21: If any time after the
commencement of the work the Cochin
Shipyard Limited shall for any reason whatsoever not require whole or part
thereof as specified in the tender to be carried out the Engineer-in-charge
shall give notice in writing of the fact to the contractor who shall have claim
to any payment of compensation whatsoever on account of any profit or advantage
which he might have derived from the
execution of the work in full, but which he did not derive in consequence of
the full amount of the work not having been made in the original
specifications, drawings, designs and instructions which shall involve any
curtailment of the work as originally contemplated.
Provided that the contractor shall be paid the charge
only of materials actually and bona fide brought to the site of the work by the
contractor and rendered surplus as a result of the abandonment or curtailment
of the work or any portion thereof and then taken batch by the contractor
provided however, that the Engineer-in-charge shall have in all such cases the
option of taking over all or any such materials at their purchase price or at local
current rates whichever may be less. In the case of such stores having been
issued from Cochin Shipyard stores, supervision charges and storages charges
shall be refunded in addition to the issue rate of materials.
CLAUSE 22. If it shall appear to the Engineer-in-charge
or his subordinate in charge of the work that any work has been executed with
unsound, imperfect or unskillful workmanship or with materials of any inferior
description or that any materials or articles provided by the Contractor for the
execution of the work
are unsound or
of a quality inferior to that contracted for otherwise not in accordance
with the contract, the contracted for or in writing which shall be made within
six months of the completion of the work from the Engineer-in-charge specifying
the work, materials or articles complained of notwithstanding that the same may
have been passed certified, forthwith rectify or remove add reconstruct the
work so specified in or paid for whole or in part, as the case may require or as
the case may be, remove materials, or articles so specified and provided other
proper and suitable materials or articles at his own proper charge and cost,
and in the event of his failing to do so within a period to be specified by the
Engineer-in-charge in his demand aforesaid then the contractor shall be liable
to pay compensation at the rate mentioned in Clause 2, while his failure to do
so shall continue and in the case of any such failure the Engineer-in-charge
may rectify or remove and re-execute the work or remove and replace with the
materials or articles complained of as the case may be at the risk and expense
in all respects of the contractor.
CLAUSE 23: All works under or in course of execution or
executed in pursuance of the
contract shall at all times be open to the inspection and supervision of the
Engineer-in-charge and his
authorized subordinates and the
contractor shall at all times during the usual working hours, and at all other
times during the usual working hours, and at all other times at which
reasonable notice of the intention of the Engineer-in-charge, or his
subordinate to visit the works shall have been given to the contractors either
himself be present to receive order and instruction, or have responsible agent
duly accredited in writing present for that purpose. Order given to the
Contractor’s agent shall be considered to have the same force as if they had
been given to the contractor himself.
CLAUSE 24: The contractor shall give not less than seven
days notice in writing to the Engineer-in-charge or his subordinate in charge
of the work before covering up or otherwise placing beyond the reach of
measurement any work in order that the same may be measured, and correct
dimensions thereof be taken before the same is so covered up or placed beyond
the reach of measurement and shall not cover up and place beyond the reach of
measurement may work without the consent in writing of the Engineer-in-charge
or his subordinate in charge of the work who shall within the aforesaid period
of seven days inspect the work and if any work shall be covered up or placed
beyond the reach of measurement without such notice having been given or
Engineer-in-charge’s consent being obtained the same shall be uncovered at the
contactor’s expense, or in default thereof no payment or allowance shall be
made for such work or the materials with which the same was executed.
CLAUSE 25: If the contractor or his working people or
servants shall break, deface, injure or destroy any part of building in which they
may be working, or any building road, road curb, fence enclosure, water pipe, cables, drains electric or telephone
post or wires, trees, grass or grass land or cultivated ground continuous to
the premises on which the work or any
part of its is being executed, or if any defect shrinkage or other faults
appear in the work within six months after a certificate final or otherwise of
its completion shall have been by the Engineer-in-charge as aforesaid arising
out of defective or improper materials or workmanship the contract shall upon a
receipt or a notice in writing in that behalf make the same good at his own
expense, or in default the Engineer-in- charge
may cause the same to be made good by
other workmen and deduct the
expenses from any sums that may be then, or at any time thereafter becomes
due to the contractor either
on this or
any other contract or from his security deposit or the proceeds of sale
thereof or of a sufficient portion thereof. The security deposit of the
contractor shall not be refunded before the expiry of six months after the
issue of the certificate final or otherwise of completion of work or till the
final bill has been prepared and passed whichever is later.
CLAUSE 26: The Contractor shall supply and provide at his
own cost all materials (except such special materials, if any, as may in
accordance with the contract be
supplied from the Engineer-in-charge's Stores), plant, tools, appliances,
implements, ladders, cordage,
tackle, scaffoldings and temporary works requisite or proper for the
proper execution of the
work whether original,
altered or substituted
and whether included in the specification or other documents forming
part of he contract or referred to in these conditions or not, or which may be
necessary for the purpose of satisfying or complying with the requirements of
the Engineer-in-charge as to any matter as to which, under those conditions he
is entitled to be satisfied, or which he is entitled to require together with
carriage, therefore to and from the work, the contractor shall also supply
without charge the requisite number of persons with the means materials,
necessary for the purpose of setting out works, and counting weighing and
assisting of the measurement of examination at any time and from time to time
of the work or materials. Failing his so doing the same may be provided by the
Engineer-in-charge at the expense of the contractor and the expenses may be
deducted from any money due to the contractor, under this or any other contract
and or from his security deposit or the proceeds of sale thereof, or of a
sufficient portion thereof.
CLAUSE 27: In every case in which by virtue of the
provisions of section 12, sub-section (1) of the workmen's Compensation Act
1623, Cochin Shipyard Limited is obliged to pay compensation to a workman
employed by the Contractor in execution of works Cochin Shipyard Limited will
recover from the contractor the amount of the compensation so paid and without
prejudice to the rights of the Cochin Shipyard Limited under section
12sub-section (2) of the said Act, Cochin Shipyard Limited shall be at liberty
to recover such amount of any part thereof by deducting it from the security
deposit of from any sum due by Cochin Shipyard Limited to the Contractor
whether under this contract or otherwise. Cochin Shipyard Limited shall not be
bound to contest any claim made against in under section 12, sub-section (1) of
the said Act, except on the written request of the Contractor and upon his
giving to Cochin Shipyard Limited full security for all costs for which Cochin
Shipyard Limited might become liable in consequence of contesting such claim.
CLAUSE 28: No labourer below the age of fourteen years
shall be employed on the work.
CLAUSE 29:
(i) Payment of wages to labourers.
The Contractor
shall make payment to labourer employed by him either directly or through
sub-contractors, wages not less than Fair Wages as defined in the Contractor’s
Labour Regulations appended herewith.
(ii) In respect of all labour directly or
indirectly employed in the works for performance of the Contractor’s part of
this agreement, the contractor shall comply with or cause to be complied with
the contractor’s Labour Regulations appended herewith in regards to all matters
provided therein.
(iii) The Engineer-in-charge shall have the
right to deduct from the moneys due to the contractor any sum requested or
estimated to be required for making good the loss suffered by a worker of
non-fulfillment of the conditions of the contract for the benefit of the
workers, non-payment of wages or deductions made from his or their wages which
are not justified by their terms of the contract or non-observance of the
Regulations.
(iv) The contractor shall comply with the
provisions of the Indian Employment of Children Act, 1933 , the payment of
wages Act, 1936. The Minimum Wages Act, 1948, the Minimum Wages ( Central)
Rules,1950, The Factory Act 1948, Employers Liability Act, 1938, Workmen’s
Compensation Act, 1923 Industrial Disputes Act, 1947, the Maternity Benefit
Act, 1961, the Model Rules for protection of health and Sanitary Arrangements
for employed and the Contractors Labour Regulation and or any modifications
thereof or any other labour laws and Rule made there under from time to time.
(v) Vis-à-vis the Cochin Shipyard Limited
the contractor shall be primarily liable to all payments to be made under and
for the observance of the regulation a foresaid without prejudice to his right
to claim indemnity from sub-contractors.
(vi) The regulations aforesaid shall be
deemed to be a part of this contract and any breach thereof shall be deemed to
be breach of contract.
CLAUSES 30: In respect of all
labour directly or indirectly employed
in the work for the performance of the agreement the contractor shall at
his own expense arrange for the safety provision as per the Appendix and or as
required by the Engineer-charge and shall at his own expense provided for all
facilities and in connection therewith. In case the Contractor fails to make
arrangement and provide necessary facilities as aforesaid he shall be liable to
pay a penalty of Rs. 50/- for each default and in addition the
Engineer-in-charge shall be at liberty to make arrangement and provide
facilities as aforesaid and recover the cost incurred in that behalf from the
Contractor.
CLAUSE 31: The contractor shall
submit, by the 4th and 19th of every month, to the Engineer-in-charge a true
statement showing, in respect of the second half of the preceding month and the
first half of the current months respectively (1) the number of labourers
employed by him on the work (2) their working hours (3) the wages paid to them
(4) the accidents that occurred during the said fortnight showing the
circumstances under which they happened and the extend of damage and injury
caused by them and (5) the number of female workers who have been allowed
Maternity benefit according to Clause 32A and the amount paid to them failing
which the contractor shall be liable to pay to Cochin Shipyard Limited a sum
not exceeding Rs. 50/- for each default of Materially incorrect statement. The
decision of the engineer-in-charge shall be final in deducting from any bill
due to the contractor the amount levied as fine.
CLAUSE 32 A: Leave and pay during
leave shall be regulated as follows:
(1) Leave:
(i) In case of
delivery, maternity leave not exceeding 8 weeks 4 weeks upto and including the
day of delivery and 4 weeks following that day.
(ii) In case of miscarriage upto
3 weeks from the date of miscarriage.
(2) Pay:
(i) In case of delivery leave pay during
maternity leave will be at the rate of the woman’s average Daily earnings,
calculated on the total wage earned on the days when full time work was done
during a period of 3 months immediately proceeding the date on which she give
notice that she expects to be confines or at the rate of rupee one a day
whichever is greater.
(ii) In case of miscarriage leave pay at the rate
of average daily earnings calculated on the total wage earned on the days when
full time work was done during a period of 3 months immediately preceding the
date of such miscarriage.
(3) Conditions for the grant of maternity leave:
No maternity
leave benefit shall be admissible to woman unless she has been employed for a
total period of not less than 6 months immediately proceeding the date on which
she proceeds on leave.
(4) The Contractor shall maintain a
register of Maternity (benefit) in the prescribed form at Annexure – III and
the same shall be kept at the place of work.
CLAUSE 33: In the event of the contractor (s)
committing a default or breach of any of the provisions of the contractor’s
committing a default or breach of any of the provisions of the contractor’s
labour Regulations and Model Rules for the protection of health and sanitary
arrangements for the workers as amended from time to time or furnishing any
information or submitting or filing any statement under the provisions of the
above regulations and rules which is materially incorrect, he/they shall
without prejudice to any other liability pay to the Cochin Shipyard Limited a
sum not exceeding Rs. 50/- for every default, break or furnishing, making,
submitting, filing such materially incorrect statements and in the event of the
contractor (s) defaulting continuously in this respect, the penalty may be
enhanced to Rs. 50/- per day for each day of default subject to a maximum of 5%
of the estimated cost of the work put to tender. The decision of the
Engineer-in-charge shall be final and binding of the parties.
Should it appear to the
Engineer-in-charge that the contractor (s) is / are not properly observing and
complying with the Model Rules for the production of health and sanitary
arrangements for work people employed by the contractor (s) (herein after
referred to as “the said Rules”) the Engineer-in-charge shall have powers to
give notice in writing to the contractor (s) requiring that the said rules be
complied with the amenities prescribed therein be provided to the work people
within a reasonable time to be specified in the notice. If the contractor (s)
shall fail within the period specified in the notice to comply with and /
observe the said rules and to provide the amenities to the work – people as
aforesaid the Engineer-in-charge shall have the power to provide the amenities
hereinbefore mention at the cost of the contractor (s). The contractor (s)
shall erect, make and maintain at his/ their own expense and to approve
standards all necessary huts and sanitary arrangements required for his/their
work people in connection with the execution of the works and if the same shall
not have been erected or constructed, according to approved standards, the
Engineer-in-charge shall have power to give notice in writing to the contractor
(s) requiring that the said huts and sanitary arrangements be remodeled and /
or reconstructed according to approved standards and if the contractor (s) fail
to remodel or reconstruct such has and sanitary arrangement according to
approved standards within the period specified in the notice, the Engineer-in-charge
shall have the power to remodel or reconstruct such huts and sanitary
arrangements according to approved standards at the cost of the contractors.
CLAUSE 34: The contractor (s)
shall at his / their own cost provide his / either labour within a sufficient
number of huts (hereinafter referred to as the camp) of the following
specifications on a suitable plot of land to be approved by the
Engineer-in-charge. No land however will be made available by the Cochin
Shipyard for the purpose of erecting huts or any other type of accommodation
for contractors labourers.
1(a) The minimum height of each hut at the
eye level shall be 7’ and the floor area to be provided will be at the rate of
3 sq.m for each member of the worker’s family staying with the labour.
(b) The contractor (s) shall in addition
construct suitable cooking places having a minimum area of 6’ x 5’ adjacent to
the hut for each family.
(c) The contractor (s) shall also
construct temporary latrine and urinals for the use of the labourers each on
the scale of not less than four per each one hundred of the total strength,
separate latrines and urinals being provided for women.
(d) The contractor (s) shall construct
sufficient number of bathing and washing places, one unit for every 25 persons
residing in the camp. These bathing and washing places shall be suitably
screened.
2(a) All the huts shall have walls of
sun-dried or burnt bricks laid in mud mortar or other suitable local materials
as may be approved by the Engineer-in-charge. In case of sun dried bricks, the
walls should be plastered with mud gobri on both sides. The floor may be katch
but plastered with mud gobri and shell be at least 6” above the surrounding
ground. The roofs shall be laid with thatched or any other materials as may be
approved by the Engineer-in-charge and the contractor shall ensure that
throughout the period of their occupation the roofs remain watertight.
(b) The contractor (s) shall provide each
hut with proper ventilation.
(c) All doors, windows and ventilators
shall be provided with suitable locks for security purpose.
(d) There shall be kept an open space of
at least 8 yards between the rows of huts which may be reduced to 20 ft. according
to the availability of site with approval of the Engineer-in-charge, back to
construction will be allowed.
3. WATER SUPPLY: The contractor (s)
shall provide adequate supply of water for the use of labourers. The provisions
shall not be less than 2 gallons of pure and wholesome water per head per day
for drinking purpose and 3 gallons of clean water per head per day for bathing,
washing purposes, where pipe water supply is available, the supply shall be at
stand pots and where the supply is from well or river, tanks which may be metal
or masonry shall be provided. The contractor (s) shall also at his / their own
cost make arrangements for laying pipelines for water supply to his / their
labour camp from the existing main whatever available and shall pay all fees
and charges therefore.
4. The site selected for the camp shall
be high ground removed from jungle.
5. Disposal of Excreta- The contractor
(s) shall make necessary arrangements for the disposal of excreta from the
latrines by trenching or incineration which shall be according to the
requirements laid down by the local Health Authorities. If trenching or
incineration is not allowed, the contractor (s) shall make arrangements for
removal of the excreta through the Municipal Committee / Authority and inform
it about the number of labourers employed so that arrangements may be made by
such committees / authority for the removal of the excreta. All charges on this
account shall be borne by the contractor and paid direct by him to the
Municipal / Authority. The contractors shall provide one sweeper for every 8
scats in case of dry system.
6. Drainage - The contractor (s) shall
provide efficient arrangements for draining away sullage water so as to keep
the camp neat the tidy.
7. The contractor (s) shall make
necessary arrangements for keeping the camp area sufficiently lighted to avoid
accidents to the workers.
8. Sanitation - The contractor (s)
shall make necessary arrangements for conservancy and sanitation in the labour
camps according to the rule of the Local Public Health and Medical Authorities.
CLAUSE 35: The Engineer-in-charge
may require the contractor to dismiss or remove from the site of the work any
person or persons in the Contractor shall forthwith comply with such
requirements.
CLAUSE 36. The contract shall not be assigned or subject without the written approval of the Engineer-in-charge. And if the contractor shall assign or sublet his contact, or attempt so to do, or become insolvent or commence any insolvency proceedings or make any composition with his creditors or attempt so to do or if any bride gratuity gift, loan for perquisite, reward or advantage pecuniary or otherwise, shall either directly, be given promised or offered by the contractor, or any of his servants or agents to any public officer or person in the employee of Cochin Shipyard Limited in anyway relating to his officer or employment, or if any such officer or person shall become in anyway relating to his officer or employment, or if any such officer or person shall of the Cochin Shipyard Limited shall have power to adopt any of the courses specified in Clause 3 as he may deem best suited to the interest of Cochin Shipyard Limited and in the event of these courses being adopted the consequences specified in the said Clause 3 shall ensure.
CLAUSE 37: All sums payable by way of compensation
under any of these conditions shall be considered as reasonable compensation to
be applied to the use of Cochin Shipyard Limited without reference to the
actual loss of damage sustained and whether or not any damage shall have been sustained.
CLAUSE 38: where the contractor is
a partnership firm, the previous approval in writing of the Engineer-in-charge
shall be obtained before any change is made in the constitution of the firm.
Where the contractor is an individual
or a Hindu undivided family business concern such approval as aforesaid shall
likewise to be obtained before the contractor enters into any partnership
agreement where under the partnership firm would have the right to carry out
the work hereby undertaken by the Contractor, if previous approval as aforesaid
in not obtained the contract shall be deemed to have assigned in contravention
of Clause 36 hereof and the same action may be taken, and the same consequences
shall ensure as provided in the said Clause 36.
CLAUSE 39: All works to be
executed under the contract shall be executed under the direction subject to
the approval in all respects of the Engineer-in-charge who shall be entitled to
direct at what points and in what manner they are to be commenced, and from
time to time carried on.
CLAUSE 40: All questions disputes
or difference or differences arising under, out of, or in connection with the
contract shall be subject to Indian laws for the time being in force and the
exclusive jurisdiction of the courts at Cochin.
CLAUSE 41: The contractor shall
fully indemnify the Cochin Shipyard Limited against any action, claims or
proceedings relating to infringement or use of any patent or design or any
alleged patent or design rights and shall pay any royalties which may be
payable in respect of any article or part thereof included in the contract. In
the event of any claims made under or action brought against Cochin Shipyard
Limited in respect of any such matters as aforesaid the contractor shall be
immediately noticed thereof and the contractor shall be at liberty, at his own
expense to settle any dispute or to conduct any litigation that may arise there
from provided that the Contract shall not be liable to indemnify the Cochin
Shipyard Ltd. if the infringement of the patent or design or any alleged patent
or design rights is the direct result of an order passed by the
Engineer-in-charge in this behalf.
CALUSE 42: When the estimate on
which a tender is made includes lump sums in respect parts of the work, the
contractor shall be entitled to payment in respect of the items of work
involved or the part of the work in question at the same rates as are payable
under this contract for such items, or if the part of the work in question is
not, in the opinion of the Engineer –in-charge capable of measurement, the
Engineer-in-charge may at his discretion pay the lump sum amount entered in the
estimate, and the certificate in writing of the Engineer-in-charge shall be final
and conclusive against the contractor with regard to any sum payable to him
under the provisions of the Clause.
CLAUSE 43: In the case of any
class of work for which there is no
specification such work shall be carried out in accordance with the instructions
and requirements of the Engineer-in-charge.
CLAUSE 44: (1) Whenever any claim
or claims for payment of a sum money arises out of or under the contract
against the contractor, Cochin Shipyard Limited shall be entitled to withhold
and also have a lien to retain such sum or sums firstly from the security
deposited with the Cochin Shipyard Limited, secondly if insufficient or if no
security taken, to withhold and have a lien to retain to the extent of the
claimed amount from any sum found payable or becoming payable to the contractor
whether under the same contract any other contract with Cochin Shipyard
Limited. Should this sum be not sufficient to cover the full amount
recoverable, the contractor shall deposit with Cochin Shipyard Limited, on
demand the balance remaining due.
It is an agreed term of the
contract that the sum of money or moneys so withheld or retained under the lien
referred of above, by Cochin Shipyard Limited will be kept withhold or retained
as such by Cochin Shipyard Limited till the claim arising out or under the
contract is determined by the arbitrator or by the competent Court or otherwise
settled by mutual agreement and that the contractor will have no claim for
interest and damage whatsoever on any account in respect of such withholding
under the lien referred to supra and duly notified in respect of such to the
contractor. For the purpose of this clause, where the contractor is partnership
firm or a limited company Cochin Shipyard Ltd. shall be entitled to withhold
and also have a lien to retain towards such claimed amounts in whole or in part
from any sum found payable to any partner/ limited company as the case may be,
whether in his individual capacity or otherwise.
(2) Cochin shipyard Limited shall
have the right to cause an audit and technical examination to the works and the
final bills of the contractor including all supporting vouchers, abstract etc.
to be made after payment of the final bill and if as a result of such audit and
technical examination any sums found to have been overpaid in respect of any
work done by the contractor under the contract or any work done by the
contractor claimed by him to have been done by him under the contract and found
not have been executed, the contractor shall be liable to refund the around of
overpayment and it shall be law full for Cochin Shipyard Limited to recover the
same from him in the manner prescribed in the sub-clause (1) of this clause or
in any other manner legally permissible and if it is found that the contractor
was paid less than what was due to him under the contract in respect of any
work executed by him under it, the amount of such underpayment shall be duly
paid by Cochin Shipyard Limited to the contractor.
Provided that Cochin Shipyard
Limited shall not be entitled to recover any sum overpaid, nor the contractor
shall be entitled to payment of any sum paid short where such payment has been
agreed upon between the Engineer-in-charge on the one hand and the contractor
on the other under any term of contract permitting payment for work after
assessment by the Engineer-in-charge.
CLAUSE 45: Any sum of money due
and payable to the contractor (including Security Deposit returnable to him)
under this contract may be withheld or retained by way of lien by Cochin
Shipyard Limited and set off against any claim of the Cochin Shipyard Ltd., for
the payment of a sum of money arising out of under any other contractor made by
the contractor with the Cochin Shipyard Ltd
It is an agreed term of the
contract that the sum of money or moneys so withheld or retained under the lien
referred to above, by Cochin Shipyard Limited will be kept withheld or retained
as by Cochin Shipyard till the claim arising out of or under the contract is
determined by the arbitrator or by the competent Court or otherwise settled by
mutual agreement and that the contractor will have no claim for interest and
damages whatsoever on this account or on any other ground in respect of any sum
of money withheld or retained under this clause and duly notified as-such to
the Contractor.
CLAUSE 46: Water required for the
work shall be given free of cost by Cochin Shipyard Ltd. Water connection shall
be given at a point within 100 meters of the work site. Contractor has to make
his own arrangements for tapping and extending the water line to the work site
after getting approval from the Engineer-in-charge.
Cochin Shipyard cannot guarantee
un-interrupted water supply due to reasons beyond its control. Hence contractor
is advised to make suitable arrangements to store water in advance for at least
a days work. Contractor shall also take maximum care to avoid wastage of water.
CLAUSE 47: Notwithstanding
anything contained to the contrary in any or all of the clause of this
contract, where any materials for the execution of the contract are procured
with the assistance of Cochin Shipyard Limited either by issue from Cochin
Shipyard stocks or purchase made under orders or permits or licenses issued by
Cochin Shipyard the Contractor shall hold the said materials economically and
solely for the purpose of the contract and not dispose of them without the
permission of the Cochin Shipyard and return, if required by the
Engineer-in-charge, all surplus or unserviceable materials that may be left
with him after the completion of the contractor or at its termination for any
reason whatsoever on being paid or credited such price as the
Engineer-in-charge shall determine having due regard to the condition of the
materials. The price allowed to the contractor however shall not exceed the
amount charged to him excluding the storage charge, if any, the decision of the
Engineer-in-charge shall be final and conclusive. In the event of breach of the
aforesaid condition the contractor shall in addition to throwing himself open
to action for contravention of the terms of the license or permit and / or for
criminal breach of trust be liable to Cochin Shipyard Limited for all moneys,
advantages or profit resulting or which in the usual course would have resulted
to him by reason of such breach.
CLAUSE 48: the contractor shall
give or provide all necessary superintendence during the execution of the works
and all long thereafter as the Engineer-in-charge may consider necessary for
the proper fulfillment of the Contractor’s obligations under the contract. The
contractor or a competent and authorised agent or representative approved in
writing by the Engineer-in-charge (which approval may at any time be withdrawn)
is to be constantly on the works and shall give his whole time to the superintendence
of the same. If such approval shall be withdrawn by the Engineer-in-charge, the
contractor shall as soon as is practicable, after receiving written notice of
such withdrawal, remove the agent from the site and shall not thereafter employ
him again on the site in any capacity and shall replace him by another agent
approved by the Engineer-in-charge. Such authorised agent or representative
shall receive on behalf of the Contractor directions and instructions from the
Engineer-in-charge or his representatives.
CLAUSE 49: The whole work may be
split up between two or more contractors or accepted in part and not in
entirely, if considered expedient.
CLAUSE 50: Sale tax or any other
tax on materials/ service in respect of this contract shall be payable by
contractor and Cochin Shipyard shall not entertain any claim whatsoever in this
respect.
CLAUSE 51: Without prejudice to
any of the rights or remedies under this contract, if the contractor dies the
Engineer-in-charge on behalf of the Cochin Shipyard shall have the option of
terminating the contract without compensation to the contractor.
CLAUSE 52: The contractor shall
not be permitted to tender for works in Cochin Shipyard Limited if any of his
near relative is posted as Accountant or as an Officer in any capacity between
the grades of Asst. General Manager, Sr. Manager (both inclusive) in that
Office. He shall intimate the names of persons who are working with him in any
capacity or are subsequently employed by him any capacity or are subsequently employed
by him and who are near relatives to any Officer in the Cochin Shipyard
Limited, Cochin. Any breach of this condition by the Contractor would render
him liable to be removed from the approved list of contractors of this company.
Note: By
the term “near relative” is meant wife husband, parents and grand parents,
children and grand children, brother and sisters unless and cousins and their
corresponding in-laws.
CLAUSE 53: No Engineer of Gazetted
rank or other Gazetted Officer employed in Engineering or Administrative duties
in an Engineering Department of the Government of India/Cochin Shipyard Limited
is allowed to work as a contractor for a period of two years of his retirement
from Government/ Cochin Shipyard service without the previous permission of
Government of India/ Cochin shipyard service without the previous permission of
Government of India /Cochin Shipyard Limited. This contract is liable to be
cancelled if either the contractor or any of his employee is found at any time
to be such person who had not obtained the permission of Government of
India/Cochin Shipyard Limited as aforesaid before submission of the tender or
engagement in the contractor’s service as the case may be.
CLAUSE 54: (i) The contractor
shall see that only the required quantities of materials are get issued. Any
such material remaining unused and in perfectly good condition at the time of
completion or determination of the contract shall be returned to the
Engineer-in-charge at a place where directed by him, if by a notice in writing
under his hand, he shall so require Credit for such materials will be given at
the prevailing market rate not exceeding the amount charged from him, excluding
the storage charges levied at the time of issue o materials to him. The contractor
shall also not be entitled to cartage and incidental charges or returning the
surplus materials from and to the stores where from they were issued.
(ii) After the completion of the
work, the theoretical quantity of cement to be used on works shall be
calculated on the basis or relevant statement approved by the DGM (Civil Engg.)
Cochin Shipyard Limited, showing the quantities of cement to be used in
different items of work, over this theoretical quantity of cement shall be
allowed a variation upto 5% plus/ minus for works the estimated cost of which
as put to tender is more than Rs. 2lakhs but upto Rs. 5lakhs upto 3% plus/minus
for works the estimated cost of which put to tender is above Rs. 5lakhs. The
difference in the quantity including authorised variations if not returned by
the contractor shall be recovered at twice the issue rate including the storage
charges, without prejudice to the provision of the relevant conditions
regarding return of materials governing the contact. In the event of its being
discovered that the quantity of cement used is less than the quantity
ascertained as hereinbefore provided (allowing variations on the minus side as
stipulated above) the cost of the quantity of cement not so used shall be
recovered from the contractor on the basis stipulated issue rates including
storage charges and cartage to site.
(iii) The Provision of the
foregoing sub-clause shall apply in the case of steel reinforcement or
structural steel section except that the theoretical quality of steel shall be
taken as the quantity required as per design or as authorised lap pages, plus
5% wastage due to cutting into pieces over this theoretical quantity, plus 5%
and minus 4% shall be allowed as variation due to wastage being more or less.
(iv) The provisions made above are
without prejudice to the right of the Cochin Shipyard Limited to take action
against the contractor or under the condition, of the contract for not doing
the work according to the prescribed specifications.
CLAUSE 55: The work (whether fully constructed or not) and
all materials, machines, tools and plant, scaffolding, temporary buildings and
other things connected there with shall be at the risk of the contractor until
the work has been delivered to the Engineer-in– charge and a certificate from
him to that effect obtained. In the
event of the work or any materials or properly brought to the site for
incorporation in the work being damaged or destroyed in consequences of
hostilities of warlike operations, the contractor shall when ordered in writing
by the Engineer–in–charge remove any debris from the site collect and properly
stack or remove in store all serviceable materials salvage from the damaged
work and shall be paid at the contractor rates, in accordance with provision of
this agreement for the work of cleaning the site of debris, stacking or removed
of serviceable materials and for the reconstruction of all work, ordered by the
Engineer–in–charge such payments being damaged or destroyed but not already
measured and paid for, the compensation shall be assessed by the
Engineer–in–charge which shall be binding on the contractor. The contractor shall be paid for the damage,
destruction suffered and for restoring the materials at the rates based on the
analysis of rates tendered for in accordance with provisions of this
agreement. The certificate of the
Engineer–in–charge regarding the quality and quantity of materials and the
rupees for which they were collected shall be final and binding on all parties
this contract.
Provided always that no
compensation shall be payable for any loss in consequence or hostilities or
warlike operations (a) unless the contractor had taken all such precaution
against Air Raid as are deemed necessary by the ARP officer or the
Engineer–in–charge (b) for any
materials etc. Not on the site of work or for any tools, plant, machinery,
scaffolding temporary buildings and other things not intended for the work.
In the event of the contractor
having to carry out reconstruction as aforesaid, he shall be allowed such
extension of time for its completion as is considered reasonable by the
Engineer–in–charge.
CLAUSE 55 A: If the contractor receives instructions from
the Cochin Shipyard Limited to insure against War risk, such insurance shall be
effected with the life Insurance Corporation of India or with such other
Government Agency which might be issuing appropriate cover for the special risk
at the cost of the Cochin Shipyard Ltd; and shall be in the joint names of the
Contractor and the Cochin Shipyard Limited.
CLAUSE 56: The security deposit
should not be refunded till clearance certificate from the Labour Officer is
obtained by the contractor.
CLAUSE 57: For the following items of works theoretical requirement of cement will be calculated at the rates given below: -
|
1. |
Cement concrete |
1:3:6 |
Using 40mm metal |
221 |
Kg / m3 |
|
2. |
Cement concrete |
1:4:8 |
Using 40mm metal |
171 |
Kg / m3 |
|
3. |
Cement concrete |
1:3:6 |
Using 20mm metal |
216 |
Kg / m3 |
|
4. |
Cement concrete |
1:2:4 |
Using 20mm metal |
330 |
Kg / m3 |
|
5. |
Cement concrete |
1:5:10 |
Using 40mm metal |
137 |
Kg / m3 |
|
6. |
Cement concrete |
1:1½:3 |
Using 20mm metal |
400 |
Kg / m3 |
|
7. |
RR masonry in CM |
1:6 |
|
72 |
Kg / m3 |
|
8. |
RR masonry in CM |
1:5 |
|
86 |
Kg / m3 |
|
9. |
Brickwork in CM |
1:5 |
|
69 |
Kg / m3 |
|
10. |
Brickwork in CM |
1:6 |
|
58 |
Kg / m3 |
|
11. |
Brickwork in CM |
1:3 |
|
116 |
Kg / m3 |
|
12. |
Plastering with CM |
1:3 |
12mm thick |
66 |
Kg / 10m2 |
|
13. |
Plastering with CM |
1:3 |
20mm thick |
96 |
Kg / 10m2 |
|
14. |
Plastering with CM |
1:4 |
12mm thick |
54 |
Kg / 10m2 |
|
15. |
Plastering with CM |
1:4 |
6mm thick |
30 |
Kg / 10m2 |
|
16. |
Pointing with CM |
1:2 |
|
18.5 |
Kg / 10m2 |
|
17. |
Guniting with CM |
1:3 |
50mm thick |
50 |
Kg / m2 |
|
18. |
Damp proof course CM |
1:4 |
12mm thick |
54 |
Kg / 10m2 |
|
19. |
Cement flushing cot |
|
|
22 |
Kg / 10m2 |
|
20. |
Half brick wall in CM |
1:4 |
|
95 |
Kg / 10m2 |
|
21. |
Hollow block masonry in CM |
1:4 |
|
58 |
Kg / 10m2 |
|
22. |
Pointing with CM |
1:3 |
|
13.25 |
Kg / 10m2 |
For all other items of work for which cement is required, the theoretical requirement of cement will be calculated as per Kerala PWD Standard Data Book.
CLAUSE 58: Labour regulations – The contractor shall undertake and execute the work with contract labour only after taking License from the appropriate authority wherever such license is required to be taken in terms of section 1(a) (b) of the contract labour (Regulation and abolition) act, 1970. The contractor shall observe and comply with the provision of all labour and industrial laws and enactments and shall comply with and implement the provisions of the Factories Act, 1948. Employees provident funds and Miscellaneous provisions Act 1952, Employees/state Insurance Act, Payment of gratuity Act, Minimum Wages Act, Payment of Wages Act, Workmen’s Compensation Act, Payment of Bonus Act, Contract Labour (Regulation and Abolition) Act and all other enactments as are applicable to him and his employees or workmen or labour engaged by him. The Contractor shall also register his employees/ workmen/ labour under the Employees/ workmen/ labour under the Employees Provident Fund & Miscellaneous Provisions Act and Regulations framed there under and under similar enactments and pay the contribution, charges and other amounts payable under the said enactments and pay the contribution, charges and other amount payable under the said enactments and shall submit all returns, statements, etc. and maintain all registers and records required under the said provisions of law. The contractor shall also furnish the names, wages and all other particulars of employees/ workmen/ labour employed by him periodically to enable the Cochin Shipyard Limited to comply with the requirements of law. If the contractor fails to pay any contributions, charges of other amounts payable under any of the aforementioned provisions of law the company shall deduct or adjust amounts equivalent to such contributions, charges or other amounts from out of any amount payable to the contractor by the Company including any deposit or amounts payable against bills and make payments on his account to the appropriate authority. The contractor shall not be entitled to question or challenge such deductions, adjustments of payments made by the Company. Any other amount payable under any law or in respect of any person employed by the contractor if not paid by the contractor shall be deducted or adjusted out of any amount payable to the contractor including any security deposit by the Company and paid over or with held for payment to such persons by the company.
CLAUSE 59: Measurement shall be as per relevant I.S. codes/CPWD specifications Volume I & II 1967. In the absence of any code dealing with a particular aspect, sound engineering practice shall prevail. Decision of the Engineer-in-charge at this aspect will be final in case there is discrepancy between Indian Standard Code and CPWD specifications, the former shall prevail.
CLAUSE 60: As regards issue of materials from store the procedure adopted by Shipyard from time to time shall be followed. No request from contractor for changing the same will be entertained. The materials which are to be issued to the contractors by CSL (shown elsewhere) will be issued only from CSL store inside the Shipyard Estate at Perumanoor and the materials should be transported to respective work spot by the contractor at his own cost.
CLAUSE 61: During execution of any item of work, if any inserts of fixtures such as conduits junction boxes for electrical wiring etc. supplied by department are to be fixed in concrete or any other works as desired by the Engineer-in-charge the fixing shall be done by the contractor free of cost unless otherwise specified in the respective item.
CLAUSE 62: VAT on Sales / Works Contract payable by the Contractor to the State Government under the KVAT Act on the net turnover of this work shall be reimbursed to the Contractor on production of documentary evidence for having actually paid the Sales Tax. Taxes as applicable under law only will be reimbursed by CSL. Any excess payment will not be considered for reimbursement.
CLAUSE 63: All rejected materials shall be removed within 3 days from the date of written order to that effect and the quantity so removed shall be made good in case the rejected materials are not removed within the specified period mentioned above the same will be removed at the cost ad risk of the contractor.
CLAUSE 64: Before commencement of the work the contractor shall establish at suitable points (as directed by the Engineer-in-charge) reference bench marks based on the standard bench mark approved by the Engineer-in-charge. The construction and maintenance of these bench marks shall be the responsibility of the contractor at his cost and risk. These reference bench marks established by the contractor shall be got checked and approved by the Engineer-in-charge at suitable intervals of time.
CLAUSE 65: All the items involving reinforcement work should include the labour charges etc for straightening the reinforcements supplied in coils. No separate rate be paid for straightening steel supplied in coils.
CLAUSE 66: The contractors are expected to read the conditions thoroughly and understand the work in all respects. If any clarification, etc are required regarding specifications, drawings, etc. the same may be obtained from the DGM (Civil Engg.) before the tender is submitted. It should be clearly be noted that the contractor has understood the tender in all respects and if any clarifications/ details are not obtained before the tender is submitted, no claim on this account will be entertained.
CLAUSE 67: If at any part of the cyclostyled tender document there is some omission or if it is illegible the fact should be brought to the notice of the DGM (Civil Engg.), Cochin Shipyard Limited and clarification obtained. If any misunderstanding is felt by the tenderer, the same also should be brought tot the notice of the DGM (Civil Engg.) Cochin Shipyard Limited and clarification obtained. No claim whatsoever shall be entertained for such purpose, after the tender is opened or during the course of the work.
CLAUSE 68: The Contractor should be registered under the KVAT Act. The VAT on works contract to be deducted at source at the time of making payment shall be recovered from the bill and remitted by CSL. Necessary Certificate in this regard will be issued to the Contractor. The Contractor should submit Form No. 20 as per the KVAT Act to facilitate CSL to deduct tax at source for each of the part payment and at the end of each quarter or before making final payment whichever is earlier, he should obtain a “No Liability Certificate” from the Sales Tax Department and furnish the same to CSL without which final payment will not be released. The Contractor shall submit his invoice in the prescribed format as per KVAT Act, which should specifically mention the KVAT charged.
CLAUSE 69: For the
completed items of the work, 75% of the net amount payable on each bill can be
paid as advance by CSL at the discretion of Dy. General Manager (Civil
Engineering), on a request by the contractor and on recommendation of the
Engineer-in-charge and production of an undertaking on approved format by the
contractor. Balance amount will be paid
after scrutiny and check of the bill.
CLAUSE 70: For all bought
out items to be used / consumed on the work, material declaration forms with
work order number shall be obtained from Security Section and the same shall be
submitted at the Office of the Engineer-in-charge along with a copy of delivery
challan / invoice drawn in favour of the contractor addressed to CSL site. Cement, steel and paint shall be purchased
from manufacturers / authorised dealers only, and shall conform to relevant
Indian Standard specification.
* * *